Estimate At Completion Cost
Estimate At Completion Cost field
The expected total cost of a schedule activity, a work breakdown structure component, or the project when the defined scope of work will be completed.
Calculated as Actual Cost plus Estimate to Complete Cost. The method for calculating estimate to complete depends on the earned value technique selected for the activity's WBS.