Estimated Time To Complete

Estimated Time To Complete field

The projected duration required to complete the remaining scope of work, work based on labor efficiency to date, assuming current performance trends continue. This estimate helps you to assess labor efficiency, forecast resource availability, and identify potential over-run of work due to declining productivity.

Calculated as Original Duration divided by Schedule Performance Index (SPI).