Exposure Finish

Exposure Finish field

The latest finish date of all activities associated with the risk.

If no activities are associated with the risk, the exposure finish date is set to the project Finish date. If the project Finish date is not set, the project Scheduled Finish date is used. If the project Scheduled Finish date is not set, the project Must Finish By date is used. If this date is not set, Exposure Finish is set to the project start date.