Forecast at Completion: Schedule (Earned Value Performance)
Forecast at Completion: Schedule field
The estimated schedule variance at completion.
For costs, calculated as Budget at Completion multiplied by Schedule Variance Index (SVI). Where SVI equals Schedule Variance divided by Planned Value Cost.
For labor units, calculated as Baseline (BL) Labor Units multiplied by Schedule Variance Index (SVI) Labor Units. Where SVI equals Schedule Variance divided by Planned Value Labor Units.