Labor Cost % Complete
Labor Cost % Complete field
The percent complete of costs for all labor resources assigned to the activity, WBS, project, or EPS.
Calculated as Actual Labor Cost divided by At Completion Labor Cost multiplied by 100. Always in the range 0 to 100.