Material Cost % Complete

Material Cost % Complete field

The percent complete of cost for all material resources assigned to the activity, WBS, project, or EPS.

Calculated as Actual Material Cost divided by At Complete Material Cost multiplied by 100. Always in the range 0 to 100.