Nonlabor Cost % Complete

Nonlabor Cost % Complete field

The percent complete of cost for all non-labor resources assigned to the activity, WBS, project, and EPS.

Calculated as Actual Nonlabor Cost divided by At Completion Nonlabor Cost multiplied by 100. It is always in the range of 0 to 100.