Performance % Complete - Labor Units

Performance % Complete - Labor Units field

The percentage of the activity or project planned work that is currently complete as measured by labor units.

Calculated as Earned Value Labor Units divided by Budget at Complete Labor Units multiplied by 100. Always in the range 0 to 100.