Placing or Removing a Hold Team Member Status Updates

To place or remove a hold on status updates:

  1. On the "" Navigation Menu, expand "" Approvals and click Status Updates.
  2. On the Status Updates page:
    1. To place a hold:
      1. Select Pending.
      2. On the status update card, select Hold.
    2. To remove a hold:
      1. Select Held.
      2. On the status update card, select Remove hold.

Tip:

  • Pending updates for a project checked out in P6 Professional or opened exclusively are not displayed until the project is checked in or the exclusive lock is released.
  • Team members can continue to make updates to activities that have not been approved yet or are on hold. The status updates will reflect the latest team member updates.