Planned Finish (Assignments)
Planned Finish field
The date the assignment is scheduled to be finished.
This date is calculated by the project scheduler but can be updated manually by the project manager. This date is not changed by the project scheduler after the activity has started. This is the finish date that P6 Team Member Web timesheet users follow and that schedule variance is measured against.