Planned Nonlabor Cost
Planned Nonlabor Cost field
The planned costs for all nonlabor resources assigned to the activity.
If no resources are assigned, calculated as Activity Planned Nonlabor Units multiplied by Project Default Price divided by Time.
Planned Nonlabor Cost field
The planned costs for all nonlabor resources assigned to the activity.
If no resources are assigned, calculated as Activity Planned Nonlabor Units multiplied by Project Default Price divided by Time.