Previewing Updates to Baselines
When you update baselines, you can choose to preview the updates that will be made to a baseline before you commit to making those changes. The Update Baselines dialog box provides an overview of all the changes that will be made to each subject area if you choose to update the baseline with the selected settings.
When you preview the changes to the baseline that will be made if you update using the options as you configured them, you can return and reconfigure the options as many times as you need to before updating the baseline. Alternatively, you can exit the preview without updating the baseline.
To preview updates to a baseline:
- On the
Navigation Menu, expand
Projects and click Activities or EPS. - On the Activities or EPS page
Tip:
If the Update Baseline Preview needs more time to complete, you can view the Update Baselines Preview in the View Service Status dialog box, by selecting the Update Baseline job and selecting View Log.