Remaining Duration (Activities)

Remaining Duration field

The total working time from the activity remaining start date to the remaining finish date.

The remaining working time is calculated using the activity's calendar. Before the activity is started, the remaining duration is the same as the planned duration. After the activity is completed the remaining duration is zero.