Remaining Float
Remaining Float field
The amount of time remaining by which the activity can be delayed before delaying the project finish date.
Calculated as Late Finish minus Remaining Finish. If the remaining finish is the same as the early finish (in general, when the activity is not started), then the remaining float is the same as the total float.