Remaining Lag
Remaining Lag field
The time lag between the activity's remaining start date and the resource's remaining start date on the activity.
If the resource's remaining work starts on the activity's remaining start date, the lag is zero. Before the activity is started, the remaining lag is the same as the planned lag.