Select Baselines Dialog Box
Overview
Use this detail window the baselines exported each time the service runs.
Screen Elements
Export on the basis of assignments: area
Project Baselines option
Determines that the assigned project baseline for each project will be exported.
User Baselines option
Determines that all the user baselines configured by the current user will be exported for each project.
Primary option
Determines that the primary user baselines configured by the current user will be exported for each project.
Secondary option
Determines that the secondary user baselines configured by the current user will be exported for each project.
Tertiary option
Determines that the tertiary user baselines configured by the current user will be exported for each project.
Export on the basis of assignments: area
Baseline ID - Name field
The name and ID of each baseline.
Assigned Baselines field
Shows whether the baseline is selected as a project, primary, secondary, or tertiary baseline.
Baseline Type field
The baseline type, used to categorize the baseline's purpose.
Data Date field
The data date for the project.
Last Updated Date field
The most recent time the project was updated.
Getting Here
- On the
Navigation Menu, expand
Administration and click Scheduled Services.
- On the Scheduled Services page, click Project.
- Click the Project Settings detail window.
- In the Baselines field, click
Select.