Splitting Resource Assignments

During your planning, you might find that some resources become overloaded with work. One way to resolve overallocation of units to a resource is to assign some of its total units to another resource.

To split resource assignments:

  1. On the "" Navigation Menu, expand "" Resources and click Planning.
  2. For the overloaded resource, select "" Context menu, select Split Resource Assignments.
  3. In the Split Resource Assignments dialog box
    1. Select a resource from the list.
    2. In the Percentage allocation to new Resource field, enter a percentage of the original resource's total units to re-assign.
    3. Click Assign.