Variance - Labor Cost
Variance - Labor Cost field
The difference between the project baseline labor cost and the at completion labor cost.
Calculated as BL Labor Cost minus At Completion Labor Cost.
Variance - Labor Cost field
The difference between the project baseline labor cost and the at completion labor cost.
Calculated as BL Labor Cost minus At Completion Labor Cost.