Variance - Nonlabor Cost
Variance - Nonlabor Cost field
The difference between the project baseline nonlabor cost and at completion nonlabor cost.
Calculated as BL Nonlabor Cost minus At Completion Nonlabor Cost.
Variance - Nonlabor Cost field
The difference between the project baseline nonlabor cost and at completion nonlabor cost.
Calculated as BL Nonlabor Cost minus At Completion Nonlabor Cost.