Calculation Tab

P6 EPPM Field P6 EPPM Table Field P6 EPPM Table Microsoft Project Field
Critical Activities critical_drtn_hr_cnt PROJECT Tasks are critical if slack is less than or equal to _ days

Note:

The currency settings exported are based on the currency selected in the User Preferences, Currency tab in P6 EPPM.