Calendar Tab

Microsoft Project Field P6 EPPM Table Field P6 EPPM Table P6 EPPM Field
Fiscal year starts in fy_start_month_num PROJECT Fiscal Year Begins
Hours Per Day day_hr_cnt CALENDAR Work Hours Per Day
Hours Per Week week_hr_cnt CALENDAR Work Hours Per Week

Note:

  • Calendars in P6 EPPM additionally have settings for Work Hours Per Month and Work Hours Per Year. Microsoft Project does not have equivalent fields. To calculate Work Hours Per Month, P6 EPPM applies the following formula: Days Per Month (as defined in Microsoft Project) multiplied by Hours Per Day. Using the value derived from this calculation, P6 EPPM applies the following formula to calculate Work Hours per Year: Work Hours per Month multiplied by 12.
  • Calendar hours per timeperiod settings in Microsoft Project are only imported if the Use assigned calendar to specify the number of work hours for each time period option is selected on the time periods page of application settings in P6 EPPM or the time periods page of admin preferences in P6 Professional.
  • Working time calendars in Microsoft Project are imported as project-level calendars. Resource working time calendars in Microsoft Project are imported as resource-level calendars.