Project Information
| Microsoft Project Field | P6 EPPM Table Field | P6 EPPM Table | P6 EPPM Field |
|---|---|---|---|
| Calendar | clndr_id | PROJECT | Default Project Calendar |
| Start Date | data_date plan_start_date | PROJECT | Data Date and Planned Start |
| Priority | priority_num | PROJECT | Project Leveling Priority |
|
Finish date (Calculated by Microsoft Project.) |
plan_end_date | PROJECT | Must Finish By |