Resource

P6 EPPM Field P6 EPPM Table Field P6 EPPM Table Microsoft Project Field
n/a auto-generated by Microsoft Project n/a ID
Resource Name rsrc_name RSRC Name
Resource ID rsrc_short_name RSRC Initials
Max Units/Time max_qty_per_hr RSRC Max Units
Price/Unit cost_per_qty RSRC Standard Rate
Price/Unit*Overtime Factor cost_per_qty*ot_factor RSRC Overtime Rate
Resource Name (of parent) rsrc_name (of parent) RSRC Group
E-Mail Address email_addr RSRC Email Address
Resource Type (labor, equipment, material) rsrc_type RSRC

Type

(work= labor or equipment, material = material)

Unit of Measure unit_abbrev UMEASURE Material Labor

Units & Prices

See units and prices sub-table.

start_date cost_per_qty cost_per_qty2 cost_per_qty3 cost_per_qty4 cost_per_qty5 RSRCRATE Cost Rate Tables
Resource Notes rsrc_notes RSRC
User Defined Field Title

User defined field

(Exchanged only if a mapping is defined for the field.)

UDFVALUE Text1 – Text30
User Defined Field Title

User defined field

(Exchanged only if a mapping is defined for the field.)

UDFVALUE Cost1 – Cost10
User Defined Field Title

User defined field

(Exchanged only if a mapping is defined for the field.)

UDFVALUE Date1 – Date10
User Defined Field Title

User defined field

(Exchanged only if a mapping is defined for the field.)

UDFVALUE Duration1 – Duration10
User Defined Field Title

User defined field

(Exchanged only if a mapping is defined for the field.)

UDFVALUE Number1 – Number20
User Defined Field Title

User defined field

(Exchanged only if a mapping is defined for the field.)

UDFVALUE Start1 – Start10
User Defined Field Title

User defined field

(Exchanged only if a mapping is defined for the field.)

UDFVALUE Finish1 – Finish10
User Defined Field Title

User defined field

(Exchanged only if a mapping is defined for the field.)

UDFVALUE Flag1 – Flag20
User Defined Field Title

User defined field

(Exchanged only if a mapping is defined for the field.)

UDFVALUE

Baseline Cost1 – Baseline Cost10

(Microsoft Project 2002 and later)

User Defined Field Title

User defined field

(Exchanged only if a mapping is defined for the field.)

UDFVALUE

Baseline Work1 – Baseline Work10

(Microsoft Project 2002 and later)

Units and Prices Sub-table

P6 EPPM Field Microsoft Project Field
Effective Date Effective Date
Price/Unit 1 Standard Rate A
Price/Unit 2 Standard Rate B
Price/Unit 3 Standard Rate C
Price/Unit 4 Standard Rate D
Price/Unit 5 Standard Rate E