Completing Activities
Mark an activity complete when you have finished your work for the activity.
To mark an activity complete:
- Select an activity.
- In the activity pane, select
Mark Activity Complete (Ctrl+Alt+C). - On the Status tab of the progress panel:
- Select Save.
Tip:
- Once you complete an activity, you can return the activity to an active state by selecting
Mark Activity In-Progress.
- If your activity entry is a milestone, select
Mark Activity Complete (Ctrl+Alt+C) and update the Started date for a start milestone, or the Finished date for a finish milestone.
- If the Update actual units when activities or assignments that were never started are marked complete in My Activities setting is selected in the General section of Application Settings and the activity you mark complete has never been updated, marking the activity complete will update the actual units for the activity to match the planned units.