Updating Activity Level Dates on a Timesheet
If you are the primary resource you can update activity level dates in a timesheet.
Note:
Your project manager can configure the project settings to prevent you from updating activity level dates in a timesheet.
To update dates in a timesheet:
In Standard View:
- Update the date in the Actual Start, Actual Finish, or Expected Finish column.
Note:
If the Actual Start, Actual Finish, and Expected Finish columns are not visible in the view, select
Customize View and move the columns from the Available Columns list to the Selected Columns list.
- Select Save.
Tip:
- Your project manager may need to approve changes to the Actual Finish date before they are applied to the project.
- You cannot select an Expected Finish date for an activity that has an Actual Finish.
- You cannot update dates on an activity in a checked out project.