Updating Progress on Steps
Update your steps to record your progress.
To update progress on a step:
- Select an activity.
- On the Activity Details tab of the progress panel:
Tip:
- Depending on the settings configured by your project manager, your % Complete for the activity may be calculated using steps. Steps either have equal weight or are weighted according to the effort required to complete the step.
- Depending on the settings configured by your project manager, you may be able to see and edit user defined fields.
- You can begin reporting progress on your steps for an activity before you start the activity.
- If you do not see the Steps section, you do not have any steps to complete on this activity and you do not have privileges to add steps to this activity.