Viewing Activities
The application automatically displays all active activities assigned to you by your project manager. You can identify critical activities by looking for the
Critical icon next to the activity. An activity is critical if a delay to the activity will delay the end of the project. You can also identify if an activity is on the longest path by looking for the Longest Path check on the Activity Details pane. Icons also identify
Due and
Overdue - Not Started (in red) or
Overdue - In Progress (in orange) activities. There are filtering, sorting, and project selection options that can be used in combination to enable you to refine your list and status your activities more efficiently.
To modify your activity view:
Tip:
- You can change the way the My Activities view is grouped by selecting Group by Project, Group by WBS, or both in Preferences.
- Filters applied in the Projects, WBS, Status, Timeframe, and Resources lists are combined with any filters you apply in the Manage Filters dialog box. If your My Activities list is empty, check that the Projects, WBS, Status, Timeframe, and Resources lists are not in conflict with the filter conditions applied in Manage Filters.