Start and Finish Dates

The dates in the start and finish columns reflect different calculated dates depending on the status of the activity.

  • Not started activities: the start and finish dates reflect the early start and early finish dates respectively.
  • In progress activities: the start date reflects the actual start date and the finish date reflects the early finish date.
  • Completed activities: the start and finish dates reflect the actual start and actual finish dates respectively.