Editing Multiple Expected Items

You can edit multiple expected items at the same time using Set Dates.

  1. When logged into Submittal Exchange, select a project and go to the log.
  2. From the Actions drop-down menu, select Edit Expected Items. OR Select the red Edit Dates link below the Due Date column
  3. Select the check box next to each item you want to edit and select Edit Selected.
  4. The Edit Selected Expected Items dialog box is displayed.
  5. Make changes to the Date Expected, Phases, Supplier/Manufacturer, or any custom column.
  6. Select the Override existing data check box if you want to override existing data. Unless this check box is selected, data will not be overwritten.
  7. Select Apply.
  8. Select Save.