Editing Multiple Expected Items
You can edit multiple expected items at the same time using Set Dates.
- When logged into Submittal Exchange, select a project and go to the log.
- From the Actions drop-down menu, select Edit Expected Items. OR Select the red Edit Dates link below the Due Date column
- Select the check box next to each item you want to edit and select Edit Selected.
- The Edit Selected Expected Items dialog box is displayed.
- Make changes to the Date Expected, Phases, Supplier/Manufacturer, or any custom column.
- Select the Override existing data check box if you want to override existing data. Unless this check box is selected, data will not be overwritten.
- Select Apply.
- Select Save.