What Email Notifications Are Sent to Architects?
Items Uploaded - Sent when General Contractors or Construction Managers upload Submittals or Closeout item and when items are uploaded only to a Posting log
Reviews Completed - Sent when the Consultants review Submittal or Closeout documents. Architects can take direct actions by using the action buttons provided in the email
Copy me on my Company Reviews - Sent when a company user uploads a reviewed item and sends it back to the General Contractor or Construction Manager
Reminders - Sent based on the Required Item Turnaround date setting in the Preference tab; these notifications inform users there are items awaiting review
Include Items Overdue from Contractor - Sent based on the Date Expected in the Full log; this setting ensures email reminder notifications are received for items awaiting submission by the Contractor or Subcontractors