Change Request Business Process

Use the Change Request business process to manage a potential change to a commitment with a vendor (Contract). It tracks key information about the change, such as the reason and amount, and is frequently a precursor to a formal Change Order.

Change requests can be created manually or they can be automatically created from other business processes such as, Architect's Supplemental Instructions (ASIs), Issues, or Requests for Information (RFIs). A Change Directive or Change Order can be created from a Change Request.

Characteristics

This is a Project-level business process with a workflow, provided in the system template.

Record Statuses

Status Resulting State
Approved terminal
Canceled terminal
Rejected terminal
Awaiting_Review non-terminal
Pending_Approval non-terminal
Sent_for_Revision non-terminal

Workflow

The default workflow for the Change Request business process is set up in a certain way; however, it may be used differently by your organization. Typically, a user with the necessary permissions can create the record and either move it directly to the end step or send it to others for review or approval. The recipients in the second step can approve or reject the record or send it on to others.

Related Processes

The Change Request business process might create the following business processes: Change Directive, Change Order

The Change Request business process might be created by the following business processes: Architect's Supplemental Instructions, Issue, Request for Information

Creating a Change Request Record

Create a Change Request record by navigating to Change Management / Change Request on the Project/Shell tab, or from the Tasks log on the Home tab or relevant Project/Shell tab. Act on an existing Change Request task that has been assigned to you from the Tasks log.

Complete the Change Request form and attach related documents, if needed. After completing the form, select Send, and select an action in the Workflow Actions list to determine the next step in the workflow. Select Send to route the form to the next assignee.

Note:

You must enter a value in all required fields (*) before you can save the form.
  1. Go to your Project tab, and switch to User mode.
  2. In the left Navigator, select Change Management, and then select Change Request.
  3. On the Change Request page, select Create. Refer to the tables below to complete the form. You can select Save at any time to save a draft version of the form. Draft versions are stored under Drafts.
  4. To add attachments, go to the Attachments tab, and select Attach Files"".
  5. After completing the form, select Send.
  6. On the Workflow Action Details tab, select who should receive this BP.
    • If permitted, you can add users to the CC list. These users will receive a notification about this BP but are not assigned a task.
    • If permitted, you can select lists of members in the Contact List section. These members also receive a notification about this BP but are not assigned a task.
    • If permitted, you can adjust task due dates for all users, or set individual task due dates for each assignee.
  7. Select Send.
  8. In the Notification window, review the content, and select OK.

    The record moves to the next step in the workflow.

Completing the Change Request Form

Key Information

Key information about this Change Request is provided below.

Field Name Access Description
Title Required Enter a title.
Contract Required Contract that is a reference to this record
Change Reason Required Reason for this change
Amount Read-Only Amount of this record or line item
Due Date Editable Target completion date for this record. A default duration has been set by your administrator but can be overridden here for this record.
Create a Change Order? Editable Use this field to create a change order automatically, upon approval of this record.

Description

Enter the description or scope of this Change Request. This information might appear in any formal printouts of this Change Request.

Field Name Access Description
Short Description Editable Enter a description of 250 characters or fewer.
Detailed Description Editable The detailed information about the short-description field. The field size can be expanded. The business processes selected for auto-creation will copy this detailed description to the destination business process.

Change Request Details

Details about the Change Request should be entered below.

Field Name Access Description
Schedule Impact (Days) Editable If available, provide an estimate for the number of additional days added by this change order.
Spec Section Editable Specification section
Need By Date Editable If applicable, the date when the change is needed

Cost and Schedule Information

Information about the cost and schedule impact of this Change Request. If this Change Request was created from another source (for example, from an RFI), the information will have carried over.

Field Name Access Description
Cost Impact Editable Indicates whether there is a cost impact
Schedule Impact Editable Indicates whether there is a schedule impact
Owner Cost Estimate Editable If there is a cost impact, this field shows the total amount of the cost impact.
Owner Schedule Impact Estimate (Days) Editable If the schedule is impacted, this field indicates the number of days that impact the schedule.
Cost Impact Notes Editable If there is a cost impact, describes the reason.
Schedule Impact Notes Editable Description of why the schedule is impacted, if a schedule impact is indicated.

Cost Tracking

Tracks the cost of this Change Request as it moves from the original estimate to the final negotiated price.

Field Name Access Description
Cost Tracking Method Editable Indicates whether the various costs should be tracked at the summary level (top-down) or rolled up from the line items (bottom-up)
Estimated Line Item Total Read-Only Estimated line item total for the change request
Estimated Amount Editable Original estimated amount for the change request
Estimated Read-Only Estimated amount for the change request
Vendor Suggested Date Editable Date when the vendor-suggested amount was received
Vendor Suggested Line Item Total Read-Only Line items total for change request that the vendor suggested
Vendor Suggested Amount Editable Amount vendor submitted for the change request
Vendor Suggested Read-Only Change requests that the vendor suggested
Recommendation Date Editable Date when the recommended amount was added
Recommended Line Item Total Read-Only Amount recommended for the change request line items, prior to negotiations
Recommended Amount Editable Amount recommended for the change request, prior to negotiations
Recommended Read-Only Final amount recommended for the change request
Final Negotiated Date Editable Date when the final date was agreed on. This is the date on which final negotiations about the date were completed.
Final Negotiated Line Item Total Read-Only Final amount agreed for the total of change request line
Final Negotiated Amount Editable Final amount agreed with the vendor
Final Negotiated Read-Only Final amount agreed for the change request

Financial Summary

The information below provides a full snapshot of the Contract and the impact of this Change Request.

Field Name Access Description
A. Original Commitment Read-Only Amount of the original contract
B. Previously Approved Change Orders Read-Only Total amount of all previously approved change orders
C. Amount Previous to this Change Order (A+B) Read-Only Revised amount of this contract, not including the current (or any pending) change orders
D. Current Request Read-Only Amount of this change order
E. Revised Contract Amount (C + D) Read-Only Revised contract amount upon approval of this change order

Reference Contract Details

The following details are pulled from the referenced contract.

Field Name Access Description
Contract Number Read-Only The unique number for the contract, which might come from a corporate financial system
Vendor Name Read-Only The name or nickname for this vendor. This field must be unique to each vendor. This name will be the primary way this company is identified in the system.
Contract Type Read-Only Type of contract
Effective Date Read-Only Enter the date this record takes effect.
Original Contract Completion Date Read-Only Target completion date of the original contract, prior to any change orders
Revised Contract Completion Date Read-Only Latest contract-completion date, based on all approved change orders
Work Retainage % Read-Only Percentage retained for work or services. The default value is set in the project setting. Can be changed at the Contract or Contract line item level.
Stored Materials Retainage % Read-Only Percentage retained on stored materials. The default value is a project setting. Can be changed at the Contract or Contract line item level.

Change Directive

To expedite the work and avoid or minimize delays in the work, which might affect the contract sum or contract time, a Change Directive can be created and sent to the Vendor.

Field Name Access Description
Create Change Directive Editable Use this field to create a Change Directive from this record immediately.

Record Information

System information about this record

Field Name Access Description
Record Number Read-Only System-assigned record number
Status Read-Only Record status for a workflow BP record is based on the workflow action preceding the current workflow step.
Creator Read-Only Creator of this record
Creation Date Read-Only Date that the record was created
Record Last Update Date Read-Only Date that the record was last updated
Business Process Record URL Read-Only A shareable link to this record, for anyone with the necessary permissions
Project Name Read-Only Name of the project
Project Number Read-Only Unique Project Number

Unit Cost Information

Information on the cost per unit for this record. The Unit of Measure values are set to the project values by default.

Field Name Access Description
Unit of Measure Editable Enter the Unit of Measure used for the Unit Quantity and Cost Per Unit amounts.
Unit Quantity Editable Unit quantity to be used to calculate the Cost Per Unit for this record
Cost per Unit Read-Only Total cost divided by the unit quantity for this record

Related Activity/Milestone

Schedule information of the selected activity/milestone

Field Name Access Description
Activity/Milestone Editable Select the activity or milestone that should be used to track the planned and actual dates in this record.
Activity Name Read-Only The name of the selected activity/milestone from Project Schedule
Planned Start Read-Only The planned start date from the selected activity/milestone
Planned Finish Read-Only The planned finish date from the selected activity/milestone
Actual Start Read-Only The actual start date for the project from the schedule activity/milestone
Actual Finish Read-Only The actual finish date from the selected activity/milestone

Currency

If the currency of this Change Request is different from the project currency, specify it here.

Field Name Access Description
Transaction Currency Editable If there are multiple currencies defined, use this field to specify a currency other than the project currency.
Rate in Project Currency Read-Only Exchange rate that will be used to calculate the Project Currency Amount. This will be set after the record is saved, submitted, or sent forward in the workflow. After it is set for a record, it cannot be changed.
Project Currency Amount Read-Only This field shows the amount of the transaction, according to the project currency.

Consolidating Line Items

Change Request line items can be consolidated from the following business processes:

  • Budget Change
  • Budget Transfer
  • Change Order
  • Change Request
  • Contract
  • Estimate
  • Forecast
  • Initial Budget
  • Invoice
  • Issue
  • Journal Entry
  • PO Amendment
  • Potential Change Order
  • Purchase Order
  • Risk
  • Work Release

Completing the Line Items tab

General

Specify a cost code for this Change Request line item.

Field Name Access Description
Cost Code Required Enter a cost code.
Code Name Read-Only Populates the code name of the selected cost code

Change Request Details

Enter the cost for this line item as a lump sum or a unit rate.

Field Name Access Description
Item Quantity Editable Enter the item quantity.
Unit of Measure Editable Enter the Unit of Measure used for the Unit Quantity and Cost Per Unit amounts.
Item Unit Cost Editable Enter the item unit cost.
Amount Read-Only Amount of this line item

Description

Enter a description for this Change Request line item.

Field Name Access Description
Short Description Required Enter a description of 50 characters or fewer.
Detailed Line Item Description Editable Enter additional detailed information about the line item description field.

Cost Tracking

If using "bottom-up" cost tracking for this Change Request, the amounts below should be used. They are then rolled up to the main form.

Field Name Access Description
Estimated Amount Editable Original estimated amount for the change request
Vendor Suggested Amount Editable Amount vendor submitted for the change request
Recommended Amount Editable Amount recommended for the change request, prior to negotiations
Final Negotiated Amount Editable Final amount agreed with the vendor

Consolidated?

If this line item has been consolidated into a Change Order, it will be indicated here.

Field Name Access Description
Consolidated? Read-Only