Project Request Business Process

Use the Project Request business process to define basic project information and automatically create a project upon approval.

Characteristics

This is a Company-level business process with a workflow, provided in the system template.

Record Statuses

Status Resulting State
Approved terminal
Canceled terminal
Rejected terminal
Awaiting_Review non-terminal
Pending non-terminal
Pending_Approval non-terminal
Project_Creation non-terminal
Sent_for_Revision non-terminal

Workflow

The default workflow for the Project Request business process is set up in a certain way; however, it may be used differently by your organization. Typically, a user with the necessary permissions can create the record and either move it directly to the end step or send it to others for review or approval. The recipients in the second step can take the action of approving or rejecting the record or send it on to others.

Related Processes

The Project Request business process might create the following business processes: BP Data Transfer (Note that BP Data Transfer will then automatically create Estimate and Project Closeout Checklist.)

The Project Request business process might be created by the following business processes: Not applicable

Creating a Project Request Record

Create a Project Request record by navigating to Company Logs / Project Request on the Company Workspace tab, or from the Tasks log on the Company Workspace or Home tab. Act on an existing Project Request task that has been assigned to you from the Tasks log.

Complete the Project Request form and attach related documents, if needed. After completing the form, select Send, and select an action in the Workflow Actions list to determine the next step in the workflow. Select Send to route the form to the next assignee.

Note:

You must enter a value in all required fields (*) before you can save the form.
  1. Go to the Company Workspace tab, and switch to User mode.
  2. In the left Navigator, select Company Logs, and then select Project Request.
  3. On the Project Request page, select Create. Refer to the tables below to complete the form. You can select Save at any time to save a draft version of the form. Draft versions are stored under Drafts.
  4. To add attachments, go to the Attachments tab, and select Attach Files"".
  5. After completing the form, select Send.
  6. On the Workflow Action Details tab, select who should receive this Project Request.
    • If permitted, you can add users to the CC list. These users will receive a notification about this Project Request but are not assigned a task.
    • If permitted, you can adjust task due dates for all users, or set individual task due dates for each assignee.
  7. Select Send.
  8. In the Notification window, review the content, and select OK.

    The record moves to the next step in the workflow.

Completing the Project Request Form

Key Information

Key Information about this Project Request

Field Name Access Description
Title Required Title of the record
Status Read-Only Status of the record
Project Number Editable Unique Project Number
Project Name Editable Name of the project
Building Editable Building for this Project Request
Location Editable Location of the project
Project Type Editable Type of project
Project Delivery Method Editable Project delivery method

Description

Information relevant to this Project Request. Supplemental information can be added as an attachment.

Field Name Access Description
Short Description Editable Enter a description of 250 characters or fewer.
Detailed Description Editable The detailed information about the short-description field. The field size can be expanded.

Assignments

Field Name Access Description
Project Sponsor Editable The sponsor of the project
Project Manager Editable Project Manager for this project
Project Coordinator Editable The coordinator of the project
Finance and Legal Responsible Officer Editable The officer responsible for finance and legal

Dates

Specify the key dates for this project, if known.

Field Name Access Description
Requested Start Date Disabled The ideal date for starting the project
Requested Completion Date Disabled The ideal date for completing the project
Project Planned Start Date Required The planned start date for the project
Project Planned End Date Editable The planned end date for the project

Project Scope

Information on the scope of this project, including any measurement estimates

Field Name Access Description
Scope / Requirement Details Editable The project Request Scope or Requirements Details
Location GSF Editable The initial Gross Square Feet (GSF) at the location site
Location NASF Editable The initial Net Assignable Square Feet (NASF) of the building
New GSF Editable The new GSF generated at location site
New NASF Editable The new NASF of the building
Renovated GSF Editable The renovated built GSF
Renovated NASF Editable The renovated built NASF
Total Affected GSF Read-Only The total affected GSF. The total GSF = New GSF + Renovated GSF
Total Affected NASF Read-Only The total affected NASF. The total NASF = New NASF + Renovated NASF

Financials

Financial-related information for the request

Field Name Access Description
Project Size Estimate Editable The estimated size of the project
Project Currency Editable Currency to be used as the project currency
Original Proposed Budget (Project Currency) Editable The Original Proposed Budget, in the Project Currency
Exchange Rate (Manual) Editable Manual exchange rate, for calculating the Original Proposed Budget in the Base Currency. 1.0 in the Base Currency should equal this amount in the project currency.
Original Proposed Budget (Base Currency) Read-Only The Original Proposed Budget, in the Base Currency
Cost Center Editable If applicable, the project cost center information
Funding Source(s) Editable

Description of any other sources for funding this project. If available, include the fund numbers.

Note:

The approval of this Project Request does not guarantee that these funds will be allocated to the project.

Project Evaluation

Evaluation information about the proposed project

Field Name Access Description
Strategic Priority Editable The strategic priority
Evaluation Score Editable The score used when evaluating the project in portfolio management
Project Year Editable The starting year of the project
Deferred Maintenance Editable Deferred Maintenance contribution of this project
Overall Project Risk Editable Risk assessment used for the Capital Planning Process

Requester Information

If this request is on behalf of another person (that is, a non-user of this system), the requester details are shown below.

Field Name Access Description
User Editable Allows for selecting a Unifier user account
Department/Business Unit Editable Primary department/business unit
First Name Editable  
Last Name Editable  
E-Mail Editable  
Title Editable  
Work Phone Editable  
Mobile Phone Editable  

Project Shell Information

For administrative use only

Field Name Access Description
Shell location Editable  
Status Editable  
Shell Templates Editable  
Project Administrator Editable Name of the project administrator
Shell Classification Editable Indicates the project classification. Classifying the project helps ensure that irrelevant projects (such as Testing Project, Training Project, and so on) are not included in any future reporting.

Record Information

Field Name Access Description
Record Number Read-Only System-assigned record number
Creator Read-Only Creator of this record
Creation Date Read-Only Date that the record was created
Record Last Update Date Read-Only Date that this record was last updated
Business Process Record URL Read-Only A shareable link to this record, for anyone with the necessary permissions