Project Status Business Process

The Project Status is typically filled in by the owner's project manager or owner's representative to report project health, status, trends, and risks to key stakeholders.

Characteristics

This is a Project-level business process with a workflow, provided in the system template.

Record Statuses

Status Resulting State
Approved terminal
Canceled terminal
Rejected terminal
Awaiting_Review non-terminal
Pending_Approval non-terminal
Sent_for_Revision non-terminal

Workflow

The default workflow for the Project Status business process is set up in a certain way; however, it may be used differently by your organization. Typically, a user with the necessary permissions can create the record and either move it directly to the end step or send it to others for review or approval. The recipients in the second step can approve or reject the record or send it on to others.

Creating a Project Status Record

Create a Project Status record by navigating to Project Management / Project Status on the Project/Shell tab, or from the Tasks log on the Home tab or relevant Project/Shell tab. Act on an existing Project Status task that has been assigned to you from the Tasks log.

Complete the Project Status form and attach related documents, if needed. After completing the form, select Send, and select an action in the Workflow Actions list to determine the next step in the workflow. Select Send to route the form to the next assignee.

Note:

You must enter a value in all required fields (*) before you can save the form.
  1. Go to your Project tab, and switch to User mode.
  2. In the left Navigator, select Project Management, and then select Project Status.
  3. On the Project Status page, select Create. Refer to the tables below to complete the form. You can select Save at any time to save a draft version of the form. Draft versions are stored under Drafts.
  4. To add attachments, go to the Attachments tab, and select Attach Files"".
  5. After completing the form, select Send.
  6. On the Workflow Action Details tab, select who should receive this BP.
    • If permitted, you can add users to the CC list. These users will receive a notification about this BP but are not assigned a task.
    • If permitted, you can select lists of members in the Contact List section. These members also receive a notification about this BP but are not assigned a task.
    • If permitted, you can adjust task due dates for all users, or set individual task due dates for each assignee.
  7. Select Send.
  8. In the Notification window, review the content, and select OK.

    The record moves to the next step in the workflow.

Completing the Project Status Form

Key Information

Key information about this Project Status is provided below.

Field Name Access Description
Title Required Enter a title.
Project Phase (Manual) Editable The phase for this project
Project % Complete Editable Percent complete for the overall project. This is entered manually and can be based on duration, costs, or progress.

Project Reporting

Reporting date and overall summary of the project Status

Field Name Access Description
Project Reporting Date Required The date the project status refers to
Project Reporting Summary Required Brief description of the current project report
Project Reporting Detailed Summary Editable Detailed description of the status of the project at the time of reporting

Project Status Summary

Enter a summary of the information related to the following items.

Field Name Access Description
Budget Status Editable The status of the project in relation to the budget
Budget Summary Editable Brief description of the budget status for the project-status period
Schedule Status Editable The status of the project in relation to the schedule
Schedule Summary Editable Brief description of the schedule status for the project-status period
Cost Status Editable The status of the project in relation to the expected cost
Cost Summary Editable Brief description of the cost status for the project-status period
Risk Status Editable Indicate the risk designation for the project. This value updates the Project details.
Risk Summary Editable Brief description of the risk status for the project status period

Project Analysis and Plans

This block should provide an indication of what has been done during the last project status period and what will be done in the next period.

Field Name Access Description
Work Completed Last Period Editable Brief description of the work that has been completed since the last project-status period
Opportunities and Challenges Editable Brief description of the opportunities and challenges for the report period
Recommended Actions Editable Brief description of the recommended actions to take during the next report period
Plans for Next Project Status Period Editable Brief description of the plans to complete for the next report period

Project Images

Add pictures showing the progress on this project, which will be included in the formal project status report. Additional images and documents can be added to the Attachments tab.

Field Name Access Description
Image 1 Editable The attached Image #1.
Image 2 Editable The attached image #2.

(Manual) Project Dates

These dates come from the Manual Project Dates block on the Project Details form and will update the Project Details form on approval of this Project Status record. If the project is linked to the Schedule on the Project Details, update the project Activity Sheet instead.

Field Name Access Description
Project Start Date Editable The actual start date of the project
Project End Date Editable The actual end date of the project
Project Planned Start Date Editable The planned start date for the project
Project Planned End Date Editable The planned end date for the project

Schedule Dates

Dates dynamically linked to the Schedule Dates block on the Project Details form that reflect the Activity Sheet in the project.

Field Name Access Description
Start Activity Name Read-Only Activity Name of the selected Start Activity/Milestone
Finish Activity Name Read-Only Activity Name of the selected Finish Activity/Milestone
Schedule Planned Start Date Read-Only Planned start date for the project, from the selected schedule activity/milestone
Schedule Planned End Date Read-Only Planned end date for the project, from the selected schedule activity/milestone
Schedule Actual Start Date Read-Only Actual start date for the project, from the selected schedule activity/milestone
Schedule Actual End Date Read-Only Actual end date for the project, from the selected schedule activity/milestone
Schedule Start Date Read-Only Start date for the project, from the selected schedule activity/milestone
Schedule End Date Read-Only Finish date for the project, from the selected schedule activity/milestone

Record Information

System information about this record

Field Name Access Description
Record Number Read-Only System-assigned record number
Status Read-Only Record status for a workflow BP record is based on the workflow action preceding the current workflow step.
Creator Read-Only Creator of this record
Creation Date Read-Only Date that the record was created
Record Last Update Date Read-Only Date that the record was last updated
Business Process Record URL Read-Only A shareable link to this record, for anyone with the necessary permissions
Project Name Read-Only Name of the project
Project Number Read-Only Unique Project Number