Risk Business Process

Use the Risk business process to record and prioritize all the risks that can occur in a project, and to propose and track the status of potential risks. Score risks using the risk matrix for both pre- and post-response plans.

Characteristics

This is a Project-level business process without a workflow, provided in the system template.

Record Statuses

Status Resulting State
Active non-terminal
Impacted non-terminal
Managed non-terminal
Open non-terminal
Proposed non-terminal
Rejected non-terminal

Related Processes

The Risk business process might create the following business processes: Action Item, Issue

The Risk business process might be created by the following business processes: Request for Information

Creating a Risk Record

Create a Risk record by navigating to Project Management / Risk on the Project/Shell tab, or from the Tasks log on the Home tab or relevant Project/Shell tab.

Complete the Risk form and attach related documents, if needed. After completing the form, select Save to create a record and keep it in editable mode, or select Submit if you are finished and ready to commit the record.

Note:

You must enter a value in all required fields (*) before you can save the form.
  1. Go to your Project tab, and switch to User mode.
  2. In the left Navigator, select Project Management, and then select Risk.
  3. On the Risk page, select Create. Refer to the tables below to complete the form. You can select Save at any time to create a record and keep it in editable mode.
  4. To add attachments, go to the Attachments tab, and select Attach Files"".
  5. After completing the form, select Submit.

Completing the Risk Form

Key Information

Key information about this Risk is provided below.

Field Name Access Description
Title Required Title of the record
Status Required Required Risks initially begin with a Proposed status until they are reviewed. Following a review, they can be set to either Open (identified as a valid risk) or Rejected (not a valid risk). After the risk impacts the project, it should be set to Active. From there, it can either become Managed (it was successfully managed by the project team) or Impacted (it impacted the project).
Risk Type Required The type of risk for risk process
Risk Priority Editable The Risk Priority list from the drop-down list
Risk Category Editable The Risk Category list from the drop-down list
Contract Editable The contract that is a reference to this record
Pre-Response Probability of Occurrence Editable The probability of the risk occurring, before mitigation actions are taken
Cost Exposure Read-Only Determines cost exposure through multiplying the potential cost amount by the pre-response probability for the risk

Description

This information might appear in any formal printouts of this item.

Field Name Access Description
Short Description Editable Enter a description of 250 characters or fewer.

Cost & Schedule Information

Estimate the impact this risk will have on the cost and schedule.

Field Name Access Description
Cost Impact Editable Indicates whether there is a cost impact
Schedule Impact Editable Indicates whether there is a schedule impact
Owner Estimate Editable If there is a cost impact, this field shows the total amount of the cost impact.
Est. Schedule Impact (Days) Editable If the schedule is impacted, this field indicates the number of days that impact the schedule.
Cost Impact Notes Editable If there is a cost impact, this field describes the reason.
Schedule Impact Notes Editable Description of why the schedule is impacted, if a schedule impact is indicated

Action to Resolve

Enter information about how this Risk will be resolved.

Field Name Access Description
Proposed Action to Resolve Editable The proposed actions to resolve the risk
Actual Action to Resolve Editable The actions that must be taken to resolve the risk
Forecasted Resolution Date Editable The date when the issue threat has been eliminated, is no longer present, or is resolved independently
Actual Resolution Date Editable Actual date of Issue Resolution
Planned Response Cost Editable The risk planned response cost
Actual Response Cost Editable The actual cost to respond to the risk
Post-Response Probability of Occurrence Editable The probability of the risk occurring, after mitigation actions are taken
Issue Record Read-Only Link to the created Issue record, after it is created from a Risk record

Detailed Description

Enter a detailed summary of the cause, description, and effect of this risk.

Field Name Access Description
Cause Editable The cause or source of the risk
Description Editable Description for risk process
Effect Editable The effect for risk process

Risk Identification and Management

Information about the identification and management of the Risk

Field Name Access Description
Identified By Editable The person who has identified the risk
Identified Date Editable The date the risk was identified
Risk Manager Editable The person currently assigned to manage the risk
Exclude from Reporting? Editable Used to exclude this record from some project or organizational reports

Risk Exposure Window

Date range to define when the Risk might occur

Field Name Access Description
Start Date Editable The start date if the risk can only occur as of a specific date (for example, weather events)
Finish Date Editable The finish date if the risk can only occur until a specific date (for example, weather events)

Risk Matrix / Risk Scoring

This block can be used to calculate a score for this risk, based on the weightings set for this project.

Field Name Access Description
Cost Impact Weighting Read-Only The weighting for the cost impact when calculating the risk score
Pre-Response Cost Impact Editable The likely cost impact of the risk before response
Post-Response Cost Impact Editable The likely cost impact of the risk after response
Schedule Impact Weighting Read-Only The weighting for the schedule impact when calculating the risk score
Pre-Response Schedule Impact Editable The likely schedule impact of the risk before response
Post-Response Schedule Impact Editable The likely schedule impact of the risk after response
Scope Impact Weighting Read-Only The weighting for the scope impact when calculating the risk score
Pre-Response Scope Impact Editable The likely scope impact of the risk before response
Post-Response Scope Impact Editable The likely scope impact of the risk after response
Reputation Impact Weighting Read-Only The weighting for the reputation impact when calculating the risk score
Pre-Response Reputation Impact Editable The likely reputation impact of the risk before response
Post-Response Reputation Impact Editable The likely reputation impact of the risk after response
Environmental Impact Weighting Read-Only The weighting for the environmental impact when calculating the risk score
Pre-Response Environmental Impact Editable The likely environmental impact of the risk before response
Post-Response Environmental Impact Editable The likely environmental impact of the risk after response
Pre-Response Risk Score Read-Only The pre-response risk score is calculated from the pre-response criteria, based on the weightings specified for the project.
Post-Response Risk Score Read-Only The post-response risk score is calculated from the post-response criteria, based on the weightings specified for the project.

Record Information

System information about this record

Field Name Access Description
Record Number Read-Only System-assigned record number
Creator Read-Only Creator of this record
Creation Date Read-Only Date that the record was created
Record Last Update Date Read-Only Date that the record was last updated
Business Process Record URL Read-Only A shareable link to this record, for anyone with the necessary permissions
Project Name Read-Only Name of the project
Project Number Read-Only Unique Project Number

Related Activity/Milestone

Schedule information of the selected activity/milestone

Field Name Access Description
Activity/Milestone Editable Select the activity or milestone that should be used to track the planned and actual dates in this record.
Activity Name Read-Only The name of the selected activity/milestone from Project Schedule
Planned Start Read-Only The planned start date from the selected activity/milestone
Planned Finish Read-Only The planned finish date from the selected activity/milestone
Actual Start Read-Only The actual start date for the project from the schedule activity/milestone
Actual Finish Read-Only The actual finish date from the selected activity/milestone

Currency

If the currency of this Risk is different from the project currency, specify it here.

Field Name Access Description
Transaction Currency Editable If there are multiple currencies defined, use this field to specify a currency other than the project currency.
Rate in Project Currency Read-Only Exchange rate that will be used to calculate the Project Currency Amount. This will be set after the record is saved, submitted, or sent forward in the workflow. After it is set for a record, it cannot be changed.
Project Currency Amount Read-Only This field shows the amount of the transaction, according to the project currency.

Consolidating Line Items

Risk line items can be consolidated from the following business processes:

  • Budget Change
  • Budget Transfer
  • Change Order
  • Change Request
  • Contract
  • Estimate
  • Initial Budget
  • Potential Change Order
  • Risk

Completing the Detailed Cost Estimate tab

Cost Information

Cost breakdown for this risk. The Potential Cost Impact should be entered as a positive number. When calculating the Cost Exposure, Threats will appear as a positive number and Opportunities will appear as negative.

Field Name Access Description
Cost Code Required Enter a cost code.
Code Name Read-Only Populates the code name of the selected cost code
Potential Cost Impact Required The full potential cost impact of the risk line item, not taking probability into account
Cost Exposure Read-Only Determines cost exposure through multiplying the potential cost amount by the pre-response probability for the risk.

Description

Description for this Risk line item

Field Name Access Description
Short Description Required Enter a description of 50 characters or fewer.
Detailed Line Item Description Editable Enter additional detailed information about the line item description field.

Risk Information

Information from the Risk record. Updates to the Risk should be reflected here as well.

Field Name Access Description
Risk Type Required The type of risk for risk process
Pre-Response Probability of Occurrence Required The probability of the risk occurring, before mitigation actions are taken

Additional Information

Enter additional information specific to this Risk line item.

Field Name Access Description
Spend Category Editable Select the spending category.
Work Package Editable Select the Work Package that this item will roll up to.

Completing the Response Actions tab

Key Information

Key information for this response action

Field Name Access Description
Title Required Title of the record
Response Action Status Required Tracks the status of the response action
Assigned To Editable The action item will be assigned to this user for resolution on the next step of the workflow.

Key Dates

Planned and Actual dates for the response action

Field Name Access Description
Planned Start Editable Planned start date of the response action
Planned Finish Editable Planned finish date of the response action
Start Editable Start date of the response action
Finish Editable Finish date of the response action

Description

Enter a brief description of the response action and provide further details on the detailed description field.

Field Name Access Description
Short Description Editable Enter a description of 250 characters or fewer.
Detailed Description Editable The detailed information about the short-description field. The field size can be expanded.

Action Item

Create an Action Item on a given date, assigned to the response action manager above.

Field Name Access Description
Create Action Item? Required Determines whether an action item should be created for this record or line item
Create Action Item On Required Date when the Action Item should be created
Target Completion Date Editable The target completion date for the action item. To be updated as needed, particularly when re-assigning an action item.
Action Item Priority Editable An integer value representing the priority of the action item
Action Item Record Editable Link to the created Action Item record, after it is created