Activity Manager
The Activity Manager node, or module, contains the following sub-nodes, when available:
- Activity Sheet
- OBS Sheet
- Rate Sheet
- WBS Sheet
To access the Activity Manager node:
- Go to the shell tab, and switch to User mode.
- In the left Navigator, select Activity Manager to expand it.
The following table provides summary details about each sub-node.
Note:
To view the Activity Sheet, or other sheets, you must have the appropriate permissions.You can create user-defined reports (UDRs) from the Activity Sheet Data Elements (DEs).
For a cost loaded schedule, Unifier does not perform any calculations in Unifier; it uses the data directly from P6.
The Activity Manager node contains the following sub-nodes:
| Sub-node name | Description |
|---|---|
| Activity Sheet |
The Activity Sheet sub-node contains a list of activity sheets listed in the Activity Sheets log. You can have multiple activity sheets. An activity sheet captures scheduling data from the mapped P6 or Oracle Primavera Cloud projects and role and resource rates from the company-level Master Rate Sheet (default) or shell-level rate sheets, and calculates the Earned Values metrics and derivatives. It is the primary source of data for the Earned Value Analysis. |
| Rate Sheet |
The Rate Sheet node captures the list of resources and roles (based on the latest data available in activity sheet) and corresponding rates from the master rate sheet. In P6 or Oracle Primavera Cloud, users can assign a role, or resource, to an activity under the Assignments tab of an activity for any project. In P6 or Oracle Primavera Cloud, rates are assigned to a role or resource at global level. To maintain the consistency, the system will import the P6 or Oracle Primavera Cloud global data to the Unifier Company Workspace. This data will be captured under a new entity called Master Rate Sheet. The rate sheet being created through P6/Oracle Primavera Cloud to Unifier integration will be saved as 'Master Rate Sheet' under a new node in Company Workspace called Master Rate Sheet. The rates (Price/Unit) for assigned roles and resources are managed at global level in P6 or Oracle Primavera Cloud, which can then be used in a project while doing the costing (calculating Present Value, Earned Value, and so on) of the project depending on the rate source (resource, role, or override) corresponding to that assignment in an activity. For a resource loaded schedule, we need rates corresponding to roles and resources for costing of any project in Unifier. There will be two types of rate sheets:
A company will only have one Rate Sheet called the "Master Rate Sheet." So, users are not allowed to create a copy sheet of the Master Rate Sheet under company workspace. This sheet will contain rates for both roles and resources, users will be able to toggle between resource and role rates from the display. By default, the rates present in master rate sheet will be used across all the resources and roles present in all activity sheets across all shells unless user has assigned another rate sheet present at the shell level to the activity sheet/project. |
| WBS Sheet |
A WBS Sheet (Work Breakdown Structure sheet) contains the following information:
The WBS Sheet node log displays the only available WBS sheet. |
| OBS Sheet |
An OBS Sheet (Organization Breakdown Structure sheet) contains the following information:
The OBS Sheet node log displays the only available OBS sheet. |
This section provides information about the System Activity Sheet. For information related to the manual activity sheets, refer to the Unifier Managers User Guide.