Creating a WBS Sheet
When an activity sheet is created, Unifier creates the WBS sheet, automatically.
About Auto-Creation
A BP record can be created automatically or manually from the WBS sheet. A new BP record can be created for any WBS, and the BP record will be permanently linked to the WBS. A WBS can be linked to one and only one BP record at a time.
In a Project, if any of the WBS Codes (the WBS Codes with line item data removed from P6) have line item data, the system dismisses the data and sets the WBS Status (uuu_cmwbs_Status) as inactive.
Note:
In the scenario above, you will notice a discrepancy between P6 and Unifier.
When you attempt to create new line items, or records, in CBS- or WBS-type BP, the WBS Picker will not display inactive WBS Codes.
In the EVM Sheet, the WBS Picker displays the all the WBS Codes, regardless of the status. This is so you can see the actuals for the WBS Code that you select.