Creating Master Rate Sheet

When you go to your Company Workspace (User mode) and select the Master Rate Sheet node, the Master Rate Sheet log opens. If there is no existing Master Rate Sheet, and you have the Create permission, the Master Rate Sheet log displays the Create option enabling you to create a new Master Rate Sheet.

Creating Master Rate Sheet Manually (Properties)

In the Master Rate Sheet log, you can create a Master Rate Sheet either through the Get Data integration or through the Create options.

Note:

If a Master Rate Sheet is available and you select Get Data, the existing Master Rate Sheet will be updated with the latest data from P6 or Oracle Primavera Cloud.

You can manually create a Master Rate Sheet in the Master Rate Sheet log if:

  • There is no Master Rate Sheet defined and present in the log, and you have the Create permission only.

    In this scenario, after you select Create, the Master Rate Sheet Properties window opens which enables you to enter a name and description for the Master Rate Sheet and select Create to open the Master Rate Sheet window.

  • There is no Master Rate Sheet defined and present in the log, and you have the Get Data permission only.

    In this scenario, you select Get Data to proceed with manually creating a Master Rate Sheet, by way of integration.

  • There is no Master Rate Sheet defined and present in the log, and you have both the Create and the Get Data permissions.

    In this scenario, you select either the Create option or the Get Data option to proceed with manually creating a Master Rate Sheet.

When the Master Rate Sheet log has an item (a Master Rate Sheet created through integration or manually), the Master Rate Sheet log displays the item Name as "Master Rate Sheet" and the item Description as "Master Sheet for Roles and Resources."

The Master Rate Sheet log will also contain the following information:

  • Last Updated
  • Created By

When the Master Rate Sheet log has an item, or an item is created, the right pane of the screen will display the following tabs:

  • Audit Log tab
  • Schedule tab
  • History tab

The Audit Log tab displays the current events through the Master Rate Sheet option when in the View (for example, when Resource - P6 or Role - P6 is selected).

This topic explains the Audit Log tab in the user-defined and P6/Oracle Primavera Cloud views for resources and roles. Events such as Create, Update, and Remove of the resources and roles in a User Defined view will be audited along with the existing audit log events for resources and roles received from P6 or Oracle Primavera Cloud.

When a resource or role is added through CSV import, only an entry per resource or role will be added in Audit Log for each successful creation of a resource or role. The Audit Log entries of the User Defined view for resources or roles are as follows:

Date Event Action Field Name Old Value New Value User Name
Date and Timestamp of the event occurred Resource > <Resource ID> or Role > <Role ID> Create Resource > <Field or Column Name> or Role > <Field Name> NA <NewValue> <Logged in Username>
Date and Timestamp of the event occurred Resource > <Resource ID> or Role > <Role ID> Update Resource > <Field or Column Name> or Role > <Field Name> <OldValue> <NewValue> <Logged in Username>
Date and Timestamp of the event occurred Resource > <Resource ID> or Role > <Role ID> Delete Resource > <Field or Column Name> or Role > <Field Name> NA NA <Logged in Username>
Date and Timestamp of the event occurred Import Create Resource > <Resource ID> NA <NewValue> <Logged in Username>

The Audit Log entries (for updated resources or roles received from P6or Oracle Primavera Cloud) when you add or update the values for the Calendar and Units/day fields are as follows:

Date Event Action Field Name Old Value New Value User Name
Date and Timestamp of the event occurred Resource > <Resource ID - Name> or Role > <Role ID - Name> Update Resource ID > Calendar <OldValue> <NewValue> <Logged in Username>
Date and Timestamp of the event occurred Resource > <Resource ID - Name> or Role > <Role ID - Name> Update Resource ID > Units/day <OldValue> <NewValue> <Logged in Username>

You can enter values in the Schedule tab fields only if you have the Get Data permission. If you create a Master Rate Sheet manually (using the Create option), there will be no details on the right pane until the data is received from the source. If the Master Rate Sheet has data coming from P6 or Oracle Primavera Cloud, the right pane shows both the Schedule and History tabs.

The History tab displays the following information:

  • Action
  • Requestor
  • Initiated On
  • Start Date
  • End Date
  • Status

The column above contains the history of the changes made to the Master Rate Sheet.