Updating Manual Activity Sheets Using Oracle Integration

You can create custom integrations in Oracle Integration and then invoke these in Unifier to get data in activity sheets or send data from activity sheets.

Prerequisites

  • The project/shell is configured to integrate with Oracle Integration.
  • In the Integration node of the Company Workspace, the Enable Integration field is set to Yes in the Connect tab of the Oracle Integration Cloud window.
  • An Oracle Integration configuration is setup with one or more integrations for manual activity sheets.
  • Ensure that you have the necessary integration permissions.

Contact your Company Administrator if any of the above prerequisites are not enabled.

Procedure

To update data in manual activity sheets by using integrations from Oracle Integration:

  1. Go to the shell tab, and switch to User mode.
  2. In the left Navigator, select Activity Manager and select the Activity Sheets node.
  3. In the right pane of the Activity Sheets select a manual activity sheet that is set up to use the integration from Oracle Integration.
  4. To get data into the manual activity sheet, select "" Get data into Activity Sheet.
    1. In the Get Data dialog box:
      1. Select any of the following options to get data:
        • Select All Projects to get data from all projects.
        • Enter a project ID to get data from a specific project.
      2. In the Type field, select Baseline.
      3. Perform any of the following actions:
        • Select OK to initiate the integration from Oracle Integration and bring the data into the manual activity sheet.
        • Select Cancel to discontinue.
  5. To send data into the manual activity sheet, select "" Send data from Activity Sheet.
    1. In the Send Data dialog box:
      1. Select any of the following options to get data:
        • Select All Projects to send activity data from all projects.
        • Enter a project ID to send data from a specific project.
      2. In the Type field, select Baseline.
      3. Perform any of the following actions:
        • Select OK to initiate the integration from Oracle Integration and send data from the manual activity sheet.
        • Select Cancel to discontinue.
  6. In the History tab of the manual activity sheet, review the job status.