About Calendars and Activities

When you select or change an activity calendar, the calendar affects the following dates and date pickers:

  • Start Date date picker
  • Finish Date date picker
  • Duration calculation
  • Actual Start Date date picker
  • Actual Finish Date date picker
  • Actual Duration
  • Forecast Start calculation
  • Forecast Finish calculation
  • Forecast Duration calculation
  • Critical Path
  • Estimate dates
  • Estimate duration
  • Float calculation
  • Progress window Progress As Of Date date picker
  • Budget and Progress options Do not allow progress entry older than the current period and Allow editing of last progress
  • Any date or date only picker data element

This is how the dates are changed when the activity calendar changes. Changes occur when the schedule sheet is refreshed.

  • Activity (not started): If the Start Date is affected by a new activity calendar, the Start Date and Finish Date will change to keep the Duration as specified. The system will use the next day on the calendar.
  • Activity (not started): If the Finish Date is affected by a new activity calendar, the system will select either a previous or next working day on the calendar.
  • Activity (in progress): If the Finish Date is affected by a new activity calendar, the system will select either a previous or next working day on the calendar. The Start Date is not affected in this case.
  • Activity (completed): No impact on Start Date or Finish Date for the activity.