Automatic launching of business processes

For BPs to launch automatically from activities, these conditions must be met:

  • Auto-control must be set to On on the Schedule Sheet properties
  • Activity is not manually controlled, which means that Auto-update Activity is selected
  • Activity has a BP setup
  • Activity has the status Not Started
  • Activity has no predecessors or the predecessors are all in Complete status
  • The Start Date for the activity is not in the future