% Complete Calculation Method options are not available
If the entry method and option settings on the Budget and Progress Method Setup window are:
- % Complete and Earned Progress entry method = Activity and resource % earned updates % complete
- % Complete Calculation Method option = Not available
- % Earned Calculation Method option = Manual activity % earned - updates resource % earned
then this data entry method scenario results:
| Activity or Resource | Data Element | Data Entry Method | |
|---|---|---|---|
| Activity | |||
| Activity % Complete |
Calculated (read-only) Same as Earned Progress |
||
| Earned Progress | Manual entry | ||
| Resource | |||
| Progress Quantity |
Calculated (read-only) Same as Earned Progress |
||
| Earned Progress |
Calculated (read-only) (Activity-level Earned Progress * Quantity) |
||