% Complete Calculation Method options are not available

If the entry method and option settings on the Budget and Progress Method Setup window are:

  • % Complete and Earned Progress entry method = Activity and resource % earned updates % complete
  • % Complete Calculation Method option = Not available
  • % Earned Calculation Method option = Manual activity % earned - updates resource % earned

then this data entry method scenario results:

Activity or Resource Data Element Data Entry Method
Activity
  Activity % Complete

Calculated (read-only)

Same as Earned Progress

Earned Progress Manual entry
Resource
  Progress Quantity

Calculated (read-only)

Same as Earned Progress

Earned Progress

Calculated (read-only)

(Activity-level Earned Progress * Quantity)