% Complete Calculation Method options are not available
If the entry method and option settings on the Budget and Progress Method Setup window are:
- % Complete and Earned Progress entry method = Activity and resource % earned updates % complete
- % Complete Calculation Method option = Not available
- % Earned Calculation Method option = Resource updates Activity - weighted avg. of resource costs
then this data entry method scenario results:
| Activity or Resource | Data Element | Data Entry Method | ||
|---|---|---|---|---|
| Activity | ||||
| Activity % Complete |
Calculated (read-only) Same as Earned Progress |
|||
| Earned Progress |
Calculated (Weighted Hours) and read-only. {Sum of [ (Resource Earned Progress / Resource Quantity) * (Resource Amount)] / Sum of (Resource Amount) } * 100 All resources will be considered |
|||
| Resource | ||||
| Progress Quantity |
Calculated (read-only) Same as Earned Progress |
|||
| Earned Progress | Manual entry | |||