% Complete Calculation Method options are not available

If the entry method and option settings on the Budget and Progress Method Setup window are:

  • % Complete and Earned Progress entry method = Activity and resource % earned updates % complete
  • % Complete Calculation Method option = Not available
  • % Earned Calculation Method option = Lead resource updates Activity and other resources

then this data entry method scenario results:

Activity or Resource Data Element Data Entry Method
Activity
  Activity % Complete

Calculated (read-only)

Same as Earned Progress

Earned Progress

Calculated (Weighted Hours) and read-only.

{Sum of [ (Resource Earned Progress / Resource Quantity) * (Resource Amount)] / Sum of (Resource Amount) } * 100

Resource
  Progress Quantity

Calculated (read-only)

Same as Earned Progress

Earned Progress

Manual Entry (Only resource that is selected under drop-down).

 

For all other resources, Earned Progress will be calculated based on (Leader Earned Progress / Leader Quantity) * Resource Quantity