Cumulative

Option 01-09 02-09 03-09 04-09 05-09 06-09 07-09 08-09 09-09 10-09 11-09 12-09
Linear 1000 2000 3000 4000 5000 6000 7000 8000 9000 10000 11000 12000
S-Curve 26.52 131.40 454.46 1243.76 2705.93 4826.86 7228.29 9349.22 10797.07 11572.10 11895.10 11999.99
On Start and Finish 600 600 600 600 600 600 600 600 600 600 600 12000

To set up budget distribution for activities at the activity level:

  1. Go to the shell tab, and switch to User mode.
  2. In the left Navigator, select Schedule Manager, and then select Schedule Sheets.
  3. In the Schedule Sheets log, select a schedule sheet, and select Open.
  4. Select an activity in the sheet.
  5. From the File menu, select Budget and Progress Setup, and then select Activity.
  6. Under the Activity Budget Distribution Profile section, choose an option.

    This option will apply specifically to the selected activity, and will override any default option set up at the schedule sheet level. The behavior of these Activity Budget Distribution Profile options at the activity level is the same as the default options at the schedule sheet level.