% Earned Calculation Method option is Lead resource updates Activity and other resources

If the entry method and option settings on the Budget and Progress Method Setup window are:

  • % Complete and Earned Progress entry method = Independently Control % complete and earned quantity
  • % Complete Calculation Method option = Lead resources updates Activity and other resources.
  • % Earned Calculation Method option = Lead resource updates Activity and other resources

then this data entry method scenario results:

Activity or Resource Data Element Data Entry Method
Activity
  Activity % Complete

Calculated (Weighted Hours) and read-only.

{Sum of [ (Resource Progress Quantity / Resource Quantity) * (Resource Amount)] / Sum of (Resource Amount) } * 100

All resources will be considered.

Earned Progress

Calculated (Weighted Cost) and read-only.

{Sum of [ (Resource Earned Progress / Resource Quantity) * (Resource Amount)] / Sum of (Resource Amount) } * 100

Resource
  Progress Quantity

Manual Entry (Only resource that is selected under drop-down). For all other resources, Progress Quantity will be calculated based on

(Leader Progress Quantity / Leader Quantity) * Resource Quantity

Earned Progress

Manual Entry (only resource that is selected under drop-down). For all other resources, Progress Quantity will be calculated based on

(Leader Earned Quantity / Leader Quantity) * Resource Quantity