% Earned Calculation Method option is Manual activity % earned and resource % earned

If the entry method and option settings on the Budget and Progress Method Setup window are:

  • % Complete and Earned Progress entry method = Independently Control % complete and earned quantity
  • % Complete Calculation Method option = Manual activity % complete and resource % complete
  • % Earned Calculation Method option = Manual activity % earned and resource % earned

then this data entry method scenario results:

Activity or Resource Data Element Data Entry Method
Activity
  Activity % Complete Manual entry
Earned Progress Manual entry
Resource
  Progress Quantity Manual entry
Earned Progress Manual entry