% Earned Calculation Method option is Manual activity % earned and resource % earned

If the entry method and option settings on the Budget and Progress Method Setup window are:

  • % Complete and Earned Progress entry method = Independently Control % complete and earned quantity
  • % Complete Calculation Method option = Resource updates Activity - weighted avg. of resource costs
  • % Earned Calculation Method option = Manual activity % earned and resource % earned

then this data entry method scenario results:

Activity or Resource Data Element Data Entry Method
Activity
  Activity % Complete

Calculated (Weighted Hours) and read-only.

{Sum of [ (Resource Progress Quantity / Resource Quantity) * (Resource Amount)] / Sum of (Resource Amount) } * 100

All resources will be considered.

Earned Progress Manual entry
Resource
  Progress Quantity Manual entry
Earned Progress Manual entry