% Earned Calculation Method option is Resource updates Activity - weighted avg. of resource costs
If the entry method and option settings on the Budget and Progress Method Setup window are:
- % Complete and Earned Progress entry method = Independently Control % complete and earned quantity
- % Complete Calculation Method option = Resource updates Activity - weighted avg. of resource costs
- % Earned Calculation Method option = Resource updates Activity - weighted avg. of resource costs
then this data entry method scenario results:
| Activity or Resource | Data Element | Data Entry Method | |
|---|---|---|---|
| Activity | |||
| Activity % Complete |
Calculated (Weighted Hours) and read-only. {Sum of [ (Resource Progress Quantity / Resource Quantity) * (Resource Amount)] / Sum of (Resource Amount) } * 100 All resources will be considered. |
||
| Earned Progress |
Calculated (Weighted Cost). {Sum of [ (Resource Earned Progress / Resource Quantity) * (Resource Amount)] / Sum of (Resource Amount) } * 100 |
||
| Resource | |||
| Progress Quantity | Manual entry | ||
| Earned Progress | Manual entry | ||