% Earned Calculation Method options are not available

If the entry method and option settings on the Budget and Progress Method Setup window are:

  • % Complete and Earned Progress entry method = Activity and resource % complete updates % earned
  • % Complete Calculation Method option = Resource updates Activity - weighted avg. of resource hours
  • % Earned Calculation Method option = Not available

then this data entry method scenario results:

Activity or Resource Data Element Data Entry Method
Activity
  Activity % Complete

Calculated (Weighted Hours) and read-only.

{Sum of [ (Resource Progress Quantity / Resource Quantity) * (Resource Amount)] / Sum of (Resource Amount) } * 100

Only hard booked resources will be considered

Earned Progress

Calculated (read-only)

Same as Activity % Complete

Resource
  Progress Quantity Manual entry
Earned Progress

Calculated (read-only)

Same as Progress Quantity