Start-to-start (SS)

When an activity's predecessor is started (for example, status = in-progress), it is also placed into an in-progress status (assuming zero lag).

  • Lag: Success, or activity will be started on forecast date
  • Lead: Success, or activity will be started on forecast date

This graphic depicts start to start conditions, lead, and lag.

Start-to-start